How we measure
Every figure on this site can be traced back to the responses operators published. These are the rules we apply.
What we collect
Every one to four minutes, depending on each source and the limits its operator sets, we fetch the status of each public charge point from the open data operators publish: their OCPI interfaces and national access points. In the United Kingdom, operators publish this data under the Public Charge Point Regulations 2023. Each response is stored exactly as received, with when and how we fetched it.
Rapid charge points only
Our figures cover rapid charge points: 50 kW and up. We work out each charge point's power from what its operator publishes about its connectors. Slower charge points in the same feed are still stored as received, but they're left out of every figure here. A charge point counts only once its operator's data has shown it to be 50 kW or more: where a feed doesn't say enough to work out the power, it stays out, and we never assume it. We count how many we leave out this way, so that gap is known rather than hidden.
We never edit the source
Operators' data is sometimes wrong: coordinates in the wrong country, missing fields, statuses that contradict each other. We never change what they published. Where we correct or interpret something, we do it in our own layer and record it as a note next to the original.
Status, in two parts
Standards describe status differently. We translate each into two questions: is the charge point in service (or faulted, unavailable, planned, removed), and is it free (or occupied, reserved, blocked)?
Every status, and how it counts
| Operator's status (OCPI) | Our category | How it counts |
|---|---|---|
| AVAILABLE | In service, free | Working |
| CHARGING | In service, occupied | Working |
| RESERVED | In service, reserved | Working |
| BLOCKED | In service, blocked (e.g. a parked car) | Not measured |
| OUTOFORDER | Faulted | Not working: out of order |
| INOPERATIVE | Unavailable (not yet active, or temporarily switched off) | Not working: inoperative |
| UNKNOWN, or a value outside the standard | Unknown | Not measured; shown as status unknown, a data-quality figure |
| PLANNED, REMOVED | Planned / removed | Not measured |
| (no fresh data) | No data | Not measured; lowers coverage |
Definitions
- Available
- Time working (available, charging or reserved), divided by the time measured (working, out of order or inoperative). This is the reliability method in the Public Charge Point Regulations 2023 and their guidance. Time that isn't measured is left out: blocked, unknown, planned, removed, and time with no data.
- Out of order
- Time reported faulted, divided by the same measured time.
- Inoperative
- Time reported inoperative (not yet active or temporarily unavailable, but not broken), divided by the same measured time.
- Status unknown
- Time the feed itself reported the status as unknown, divided by all the time it reported anything. A high figure means the feed says little about its chargers; it isn't counted as up or down.
- Coverage
- The time the feed told us anything, divided by the time in the period, across all charge points. It's always shown next to availability.
- Against the 99% rule
- The regulations require a rapid network to be reliable 99% of the time on average over each calendar year. Our figures use the same method over the period shown, from published data alone. An operator's own figure can differ: it also leaves out time outside a charge point's opening hours, and downtime it can show was outside its control.
- Charge points
- A count, not an average: the number of rapid charge points on the latest day of the period shown. A charge point that was there earlier in the period still counts towards the times, but not towards the number.
- A network's figure
- We combine a network's charge points as all their working time divided by all their measured time: the ratio of means in the government's guidance (3.4.4), so every measured minute counts the same. The government's reporting template averages each charge point's figure instead, so every charge point counts the same. The two differ when charge points were measured for different lengths of time, for example one added during the year. We're confirming with the Office for Zero Emission Vehicles that the ratio of means is the compliance figure; operator packs show both.
- No data
- An observation counts for twice the interval at which its source publishes (two minutes for a feed fetched every minute). Beyond that, the time is "no data". Whole days without data are shown as missing, never estimated, and filled in if the data arrives later.
- Days
- Local days: UK time for UK sources, so the days the clocks change have 23 or 25 hours. Months, quarters and years are built from days.
Recalculation
Late data, corrections and improvements to our methods are applied by recalculating from the stored responses. A recalculated day replaces the old one; nothing is ever counted twice.